Software Engineering - Spiral Model | VCMIT



Spiral Model

The spiral model, initially proposed by Boehm, is an evolutionary software process model that couples the iterative feature of prototyping with the controlled and systematic aspects of the linear sequential model. It implements the potential for rapid development of new versions of the software. Using the spiral model, the software is developed in a series of incremental releases. During the early iterations, the additional release may be a paper model or prototype. During later iterations, more and more complete versions of the engineered system are produced.


Each cycle in the spiral is divided into four parts:

Objective setting: Each cycle in the spiral starts with the identification of purpose for that cycle, the various alternatives that are possible for achieving the targets, and the constraints that exists.

Risk Assessment and reduction: The next phase in the cycle is to calculate these various alternatives based on the goals and constraints. The focus of evaluation in this stage is located on the risk perception for the project.

Development and validation: The next phase is to develop strategies that resolve uncertainties and risks. This process may include activities such as benchmarking, simulation, and prototyping.

Planning: Finally, the next step is planned. The project is reviewed, and a choice made whether to continue with a further period of the spiral. If it is determined to keep, plans are drawn up for the next step of the project.

The development phase depends on the remaining risks. For example, if performance or user-interface risks are treated more essential than the program development risks, the next phase may be an evolutionary development that includes developing a more detailed prototype for solving the risks.

The risk-driven feature of the spiral model allows it to accommodate any mixture of a specification-oriented, prototype-oriented, simulation-oriented, or another type of approach. An essential element of the model is that each period of the spiral is completed by a review that includes all the products developed during that cycle, including plans for the next cycle. The spiral model works for development as well as enhancement projects.

When to use Spiral Model?


  • When deliverance is required to be frequent.
  • When the project is large
  • When requirements are unclear and complex
  • When changes may require at any time
  • Large and high budget projects


Advantages


  • High amount of risk analysis
  • Useful for large and mission-critical projects.


Disadvantages


  • Can be a costly model to use.
  • Risk analysis needed highly particular expertise
  • Doesn't work well for smaller projects.




Comments

Popular posts from this blog

Create House Like Structure Perform Operations Program In C | VCMIT

Program to create a house like figure and perform the following operations.  Scaling about the origin followed by translation.  Scaling with reference to an arbitrary point. Reflect about the line y = mx + c. INPUT #include <stdio.h> #include <graphics.h> #include <stdlib.h> #include <math.h> #include <conio.h> void reset (int h[][2]) { int val[9][2] = { { 50, 50 },{ 75, 50 },{ 75, 75 },{ 100, 75 }, { 100, 50 },{ 125, 50 },{ 125, 100 },{ 87, 125 },{ 50, 100 } }; int i; for (i=0; i<9; i++) { h[i][0] = val[i][0]-50; h[i][1] = val[i][1]-50; } } void draw (int h[][2]) { int i; setlinestyle (DOTTED_LINE, 0, 1); line (320, 0, 320, 480); line (0, 240, 640, 240); setlinestyle (SOLID_LINE, 0, 1); for (i=0; i<8; i++) line (320+h[i][0], 240-h[i][1], 320+h[i+1][0], 240-h[i+1][1]); line (320+h[0][0], 240-h[0][1], 320+h[8][0], 240-h[8][1]); } void rotate (int h[][2], float angle) { int i; for (i=0; i<9; i++) { int xnew, ynew; xnew = h[i][0] * cos (angle) - h[i]

Software Engineering - Waterfall Model | VCMIT

Waterfall model Winston Royce introduced the Waterfall Model in 1970.This model has five phases: Requirements analysis and specification, design, implementation, and unit testing, integration and system testing, and operation and maintenance. The steps always follow in this order and do not overlap. The developer must complete every phase before the next phase begins. This model is named "Waterfall Model", because its diagrammatic representation resembles a cascade of waterfalls. 1. Requirements analysis and specification phase: The aim of this phase is to understand the exact requirements of the customer and to document them properly. Both the customer and the software developer work together so as to document all the functions, performance, and interfacing requirement of the software. It describes the "what" of the system to be produced and not "how."In this phase, a large document called Software Requirement Specification (SRS) document is created whic

Software Engineering - Agile Model | VCMIT

Agile Model The meaning of Agile is swift or versatile."Agile process model" refers to a software development approach based on iterative development. Agile methods break tasks into smaller iterations, or parts do not directly involve long term planning. The project scope and requirements are laid down at the beginning of the development process. Plans regarding the number of iterations, the duration and the scope of each iteration are clearly defined in advance. Each iteration is considered as a short time "frame" in the Agile process model, which typically lasts from one to four weeks. The division of the entire project into smaller parts helps to minimize the project risk and to reduce the overall project delivery time requirements. Each iteration involves a team working through a full software development life cycle including planning, requirements analysis, design, coding, and testing before a working product is demonstrated to the client. Phases of Agile Model